This is a continuation of Phase 1 of the project. The project was awarded to KMC Enterprise at price of approximately SCR 1,765,635.
The project encountered delays due to way leave issues .The original alignment of the road had be to diverted and this has come a considerable amount of extra work in the form of large retaining wall and earth works So far the project is progressing quite well and it’s at 55% completion.