Fond Azor – Baie St Anne Praslin

>
>
Fond Azor – Baie St Anne Praslin

The road is around 350metres long and it will facilitate access to the Fond D‘Azor Land Bank project implemented by the Ministry. The road project started in 2016 and in 2018 the contract for the project was dismissed. In 2019 the remaining part of the project equivalent to 135metres of road was re initiated. Presently the project is ongoing and aims to be completed in April 2020. This phase of the project amounts to a value of Rs. 260,000.