The Pasquere project is to link Anse Boudin area to Grand Anse via the La Plaine Holandaise road. In total the road is 3 kilometers with an estimated cost of Rs. 46million. The project is being undertaken in different phases and it started in August 2019. The first phase is targeted to be completed by end of April at a cost of Rs.5.4million. The total length of road being covered under the Phase I is around 500metres. The third phase of the project which will be a continuation of the Phase I is currently awaiting approval to tender and expected to start during the second quarter of 2020. The total length of road expected to be covered under the phase III will be around 400metres.